PIPE: Fabrication of Spools; Carbon, Alloy, High Strength Special, Low and High Temperature Steels | INSPECTION & TESTING

TEST AND INSPECTION PER: 01-SAMSS-010 and specifications as noted below.

PIPE: Fabrication of Spools; Carbon, Alloy, High Strength Special, Low and High Temperature Steels

Pre-Fabrication/Production Requirements

Specification Details / Notes:

Pre-Inspection Meeting Verify Company approval of manufacturer’s Inspection and Test Plan / Quality Plan
Material Test Reports Per Applicable SAMSS
Welder Qualification Records & Repair Rate Tracking SAES-W-011 and/or W-012 and ASME IX.
Weld Procedure Qualification Records, Weld Procedure Specifications and Weld Table SAES-W-011 and/or W-012 and ASME IX. Company approval required.
NDT Personnel and Procedures Verify valid personnel qualification and approved procedures.

In process inspection & test requirement

Specification Details / Notes:

Weld Joint Preparations 01-SAMSS-010 & SAES W-011 or 012 as required
Preheat 01-SAMSS-010 & SAES W-011 or 012 as required
Full Penetration Welding achieved on 2″ or Smaller Weld Bosses 01-SAMSS-010 & SAES W-011 or 012 as required.
Visual Weld Inspection & Workmanship 01-SAMSS-010 & SAES W-011 or 012. Shall be performed prior to NDT.
Post Weld Heat Treatment (if required) 01-SAMSS-010 & SAES W-011 or 012. Shall be performed prior to final NDT.
Impact test and Hardness test(if required) Per applicable standard.
Dimensional Inspection Per 01-SAMSS-010 and PO requirement
NDT Per 01- SAMSS-010 , SAES W-011 or 012 and applicable standard

Final inspection & test requirements

Specification Details / Notes:

 

Visual and Dimensional Inspection and Verification of Marking Per 01-SAMSS-010 and PO requirement
Hydrostatic Test (if required) Per 01-SAMSS-010, code and PO requirement.
Painting Per P.O requirement.
Marking, Spool Identification, cleaning, End Protection and shipment Per 01-SAMSS-010, Codes and PO requirement.

Notes:

  • May only be waived by the responsible Saudi Aramco, ASC, AOC Inspection
  • See form SA175 – 000003 for instructions on using this
  • Extent of witnessing shall be decided during the pre inspection meeting

PIPE: Fabrication of Spools; Carbon, Alloy, High Strength Special, Low and High Temperature Steels | INSPECTION & TESTING

PIPE: Fabrication of Spools; Carbon, Alloy, High Strength Special, Low and High Temperature Steels | INSPECTION & TESTING

PIPE: Fabrication of Spools; Carbon, Alloy, High Strength Special, Low and High Temperature Steels | INSPECTION & TESTING

 

Leave a Reply

Your email address will not be published. Required fields are marked *