SAES-T-629 PDF – Telecommunications Buried Cable and Wire

This article is about SAES-T-629 which is about Telecommunications Buried Cable and Wire and download SAES-T-629 PDF for telecommunication and electrical engineers, supervisors and project managers, telecom QCs, telecom QC Supervisors. This is saudi aramco standards of Telecommunication Engineering based on international codes and standards and useful for telecom and electronics engineering knowledge to get job as engineers, QC Supervisors and QC managers, Engineering managers and technicians.

SAES-T-629 PDF Download

SAES-T-629

Telecommunications Buried Cable and Wire

The SAES-T-629 standard provides mandatory design requirements for the direct burial of telecommunications cable and wire. This standard ensures that the direct burial installations meet the necessary specifications and guidelines for reliable and efficient communication infrastructure. The standard covers various aspects of the design process, including cable selection, trenching, backfilling, and grounding. Compliance with SAES-T-629 helps ensure the proper installation and protection of telecommunications cables and wires when buried directly in the ground, reducing the risk of damage and maintaining the integrity of the communication system.

Design General Requirements

Design Requirements for OSP Telecommunications Cable and Wire Installation

4.1 General Requirements

4.1.1 OSP Design Reference

  • The BICSI Outside Plant Design Reference Manual (current version) is the recognized detailed design information for OSP design.
  • Design drawings should use conventional symbols as specified in SAES-T-018 Telecommunications – Symbols, Abbreviations, and Definitions.

4.1.2 OSP Designer Certification Requirements

  • Non-Aramco design offices must have a valid/current BICSI Registered Communications Distribution Design (RCDD) and/or OSP Specialty certification for OSP telecommunications system designs.
  • For external design contractors, the RCDD and/or OSP specialist must be a direct employee of the company.
  • Design drawings must be stamped by the RCDD and/or OSP specialist before the package can be Issued for Construction (IFC).

4.1.3 Cable Protection during Construction

  • Cables should be protected from being driven over by highway traffic, construction equipment, vehicles, or any activity that could damage the cable.
  • Direct buried telecommunication cables must be placed at minimum depths as specified in SAES-T-928.

4.1.4 Buried Cable Crossings of Streets, Roads, and Highways

  • Buried cable crossings of streets, roads, and highways must comply with SAES-T-928.

4.1.5 Road and Railroad Crossings

  • Road and railroad crossings must be constructed in accordance with SAES-T-928, SAES-T-911, and any relevant government requirements when government roads are involved.

4.1.6 Telecommunication Cables Near Power Facilities

  • Telecommunication cables placed near power facilities must be installed in accordance with SAES-T-928.

4.2 Joint Buried Cable Installation

4.2.1 Joint Trench Construction with Power Facilities

  • The “Random Separation” joint trench method is not allowed for joint trench construction with power facilities.
  • Joint buried construction with power facilities requires fixed separation as indicated in SAES-T-928.

4.2.2 Joint Pedestals for Power and Telecommunication Cables

  • Joint pedestals for power and telecommunication cables should not be used.
  • Telecommunication terminal housings/pedestals located within 3 m (10′) of power apparatus or vertical pole grounds (MGN) must have their grounding systems bonded together according to SAES-T-928.

4.2.3 Excavations and Restorations

  • All excavations and restorations must be carried out in accordance with the Saudi Aramco “Safety Management System (SMS).”

4.2.4 Electrical Station Protection

  • Electrical station protection should be installed in accordance with SAES-T-887.
  • Additional electrical protection requirements are outlined in SAES-T-887 and SAES-T-903.

4.4 Buried Cable Signs – Description and Installation

  • The installation information for buried/underground cable route marker posts and signs can be found in Saudi Aramco Drawing AB-036897.
  • Marker post/sign locations must be indicated on the construction drawings.
  • Marker/Identification tape should be placed in accordance with SAES-T-928.

4.5 Joint Buried Cable – Maintenance/Emergency Safety Precautions

4.5.1 Exposing Existing Communications Facilities

  • Existing communications facilities must always be exposed using hand digging.
  • Hand digging tools used should have handles made of wood or other materials with comparable insulating value.
  • If power cables are to be exposed, the Power Distribution Department (PDD)/Proponent should be present on-site prior to or during the excavation to provide appropriate advice.
  • Insulated rubber gloves, suitably certified, must be worn while digging and examining the markings and outside structure of the cables during the visual inspection of excavated cables.

4.5.1.1 Temporary Bonding

  • After identifying the proper telephone cable and before breaking the cable metallic shield, a temporary bond must be placed across the area to be opened to minimize differences in electrical potentials.

4.5.1.2 Handling Power Cables

  • Telecommunications personnel must not move or bend power cables at any time.
  • As stated in Para. 4.2.3.1, the Power Distribution Department/Proponent must be requested to identify and reposition power cables as necessary.

4.5.2 Damage to Power and Telecommunication Cables

  • In the event that both a power cable and a telecommunication cable are damaged in the same excavation, the power cable should typically be repaired first.
  • However, repair of the telecommunications cable must not begin until both the supervisor and PDD/Proponent have determined that safe working conditions have been restored.

FAQs about SAES-T-629 PDF Download

  1. What is the purpose of the SAES-T-629 standard?

    The SAES-T-629 standard provides mandatory design requirements for the direct burial of telecommunications cable and wire. It ensures that installations meet specifications for reliable and efficient communication infrastructure.

  2. What aspects of the design process does SAES-T-629 cover?

    SAES-T-629 covers various aspects of the design process, including cable selection, trenching, backfilling, and grounding.

  3. What is the significance of compliance with SAES-T-629?

    Compliance with SAES-T-629 ensures proper installation and protection of telecommunications cables and wires when buried directly in the ground. It reduces the risk of damage and helps maintain the integrity of the communication system.

  4. What is the OSP Design Reference mentioned in the standard?

    The BICSI Outside Plant Design Reference Manual is the recognized detailed design information for OSP design referred to in SAES-T-629.

  5. What symbols should be used in design drawings according to SAES-T-629?

    Design drawings should use conventional symbols as specified in SAES-T-018 Telecommunications – Symbols, Abbreviations, and Definitions.

Read Also:

SAES-T-628 PDF Download – Telecommunications Underground Cable

SAES-T-625 PDF Download – Inter and Intra Building Fiber Optic Communication Cables

SAES-T-624 PDF Download – Telecommunications Outside Plant – Fiber Optics

SAES-T-603 PDF Download – Telecommunications Safeguards and Warning Devices

SAES-T-566 PDF Download – Plant Demilitarized Zone (DMZ) Architecture

SAES-T-556 PDF Download – Circuit Quality and Performance

SAES-T-555 PDF Download – IP Based Closed-Circuit Television (CCTV)

SAES-T-521 PDF Download – Circuit Measuring Techniques

SAES-T-494 PDF Download – Very Small Aperture Terminal (VSAT) Network Design

SAES-T-493 PDF Download – Digital Trunked Radio System

SAES-T-492 PDF Download – VHF/UHF Land-Mobile and Fixed Radio Communication

SAES-T-481 PDF Download – In-Plant Voice Paging System

SAES-T-360 PDF Download – Synchronous Digital Hierarchy Transmission Systems

SAES-T-151 PDF Download – D.C. Power Systems

SAES-T-101 PDF Download – Regulated Vendors List for Communications Equipments and Materials

SAES-T-018 PDF Download – Telecommunications Symbols, Abbreviations and Definitions

SAES-T-000 PDF Download – Telecommunications Standards – Introduction and Indices