Cathodic Protection Quality Assurance System

12.1.1 Each stage or element of the CP system, or both, for example design, installation, and testing, shall be documented and recorded in accordance with ANSI/ASQC Q9001 quality assurance plan. This quality assurance plan shall be used in design/development, installation and servicing.

12.1.2 Each stage of the design, design amplification or design verification shall be checked and documented.
12.1.3 Appropriate visual and mechanical or electrical testing, or both, shall be carried out for every stage of the installation work shall be documented.
12.1.4 Test instruments shall have valid calibration certificates traceable to international standards of calibration.
12.1.5 The quality documentation shall constitute part of the permanent record of the works.

Cathodic Protection Installation 

Installation of Cathodic protection systems shall be in accordance with the CP contractor procedures after SABIC STC review and approval:

Cathodic Protection Commissioning, Operation and Maintenance

For commissioning, operation and maintenance of CP system, see SES L02-M01.