This article is about Commercial HVAC System Complete Inspection and Checklist as per International Codes and standards.
Commercial HVAC System Complete Inspection and Checklist
- Verify that the Testing Adjusting and balancing (TAB) report has been reviewed and approved by the concerned HVAC maintenance/ operation organization.
- Verify that HVAC units automatically shut down when fire alarm system is activated,
- Verify that Fire Dampers bear a label from a recognized testing laboratory or tested in accordance with the requirements of UBC STD 43-7 or UL-555.
- Verify that filters and strainers used during construction have been cleaned or replaced
- Verify that all the quality record documents are available at the construction site
- Verify that all the quality record documents are complete
- Verify that all the Quality Record document have been reviewed
Note: Check for all the applicable signatures in various test forms, etc” - All non-conformance reports and worksheets shall have been resolved to the satisfaction of Inspection Department or entered on the MCC Exception Item List and classified as a “No” item.
- All Operation and Maintenance (O&M) manuals have been submitted to the Proponent for review four (4) weeks prior to MC.
Note: Process O&M manuals for facilities must be approved by the Proponent before MC.”
Standards Codes and References For Commercial HVAC System
- SAES-K-001 – Heating, Ventilating and Air Conditioning (HVAC).
- SAES-K-100 – Saudi Aramco Mechanical (HVAC) Code.
- Uniform Mechanical Code (UMC).
- Uniform Fire Code (UFC), 1997.
- HVAC Passively Cooled Shelter Receiving Insepction.
- Fan Coil Receiving, Handling, Storage and Preservation Checklist
- HVAC Metal Duct, Hangers and Supports and Insulation Receiving.
- HVAC Chilled Water Piping Lay-out and Support.
- HVAC Condensate Drain Installation | HVAC Engineering.
- HVAC Two Way and Three Way Control Valve Arrangement (Chilled Water Lines).
- HVAC Air Handling Unit (AHU) Installation | HVAC Engineering.
- Air Cooled Condenser Installation | Design | Technical Specification.
- Chilled Water System Components Receiving, Handling, Storage and Preservation Inspection.
- HVAC Exhaust Fan Receiving, Handling and Preservation.
- HVAC Air Handling Unit (AHU) Receiving, Handling, Storage and Preservation..
- HVAC Duct System Handling, Storage and Preservation.
- Commercial Kitchen Hood Installation | Selection | Technical Specification.