How to Cut Control Joints in Concrete Slab?


Concrete slabs are prone to developing cracks as they undergo shrinkage. To mitigate this issue, control joints are incorporated into the design of the slab. These joints are strategically placed and cut to control the formation of cracks and ensure that they occur at predetermined locations.

The effectiveness of control joints in reducing cracks in concrete slabs is largely dependent on the specifications of the joint. The depth of the cut, timing of the cut, and location of the joint are all critical factors that impact the success of the joint in controlling cracks.

When properly designed and implemented, control joints can significantly reduce the occurrence and severity of cracks in concrete slabs. However, if the joint is not appropriately placed or cut to the right depth, it may fail to control the formation of cracks, resulting in unsightly and potentially hazardous structural damage. Therefore, careful attention must be paid to the specifications of control joints during the design and construction phases to ensure their effectiveness.

How to Cut Control Joints in Concrete Slab?
Fig 1: Sawing of control joint in concrete slab.

The focus of this article is to provide a comprehensive understanding of the technical specifications required to cut control joints. These specifications are crucial for anyone involved in the cutting of control joints, as they ensure that the process is carried out with precision and accuracy. By adhering to these specifications, the final product will be of high quality and meet the required standards. Therefore, it is important to have a sound understanding of the technical specifications before attempting to cut control joints. This article aims to provide a clear and concise explanation of the key technical specifications that should be considered.

1. The Timing of the Control Joint Cut

Efficient use of control joints in concrete slabs requires careful consideration of various factors. The timing of saw-cutting the concrete slab plays a crucial role in ensuring the effectiveness of control joints. Several factors, such as concrete mix, weather conditions, hardness of concrete, and types of machines used for making the control joints, determine when to cut the concrete slab.

Sawing the concrete slab with a blade before it has reached its initial setting time can lead to a weakened edge along the joint, causing the aggregates to strew out of the slab. This undesirable effect is known as Ravelling. On the other hand, sawing too late can result in uncontrolled cracking as the concrete contracts during curing.

The weather conditions during the saw-cutting process also affect the timing of making control joints. In hot weather conditions, sawing can begin four hours after pouring the concrete, whereas in cold weather conditions, sawing can begin after 12 hours.

To determine the appropriate time for saw-cutting, it is best to conduct trial cuts and check for ravelling. Once the ravelling stops during these trial cuts, saw-cutting should commence immediately. By following these guidelines, control joints can be effectively utilized to ensure the longevity and stability of concrete slabs.

2. Location of Control Joint


Control joints are an essential aspect of concrete slab construction. It is recommended that these joints be placed at the center of the slab to divide the concrete into equal segments. The spacing of these joints should be in the range of 24 to 36 times the thickness of the concrete slab. However, if high shrinkage concrete is used, it might be necessary to decrease the cut spacing.

When constructing a concrete slab, the location of the control joints is determined by several factors. First, the joints must be continuous, forming a square pattern. This pattern ensures that the segments formed by the joints are uniform in shape and size. Secondly, the ideal location for the joints is where the steel reinforcement is less or not found. This placement helps prevent cracking that could occur due to differential movement between the concrete and steel.

The size of the segments formed by the control joints can vary depending on the climate conditions. For instance, in hot climatic conditions, the segments may be larger than conventional segments due to the fast setting of concrete in a big area. Ultimately, the purpose of the control joints is to control and minimize cracking in the concrete slab. By placing them strategically, it is possible to ensure that the slab remains structurally sound for years to come.

3. Depth of the Control Joint

When laying a concrete slab, it is important to ensure that proper measures are taken to prevent random cracking and ensure that the slab can transfer loads effectively. One such measure is the use of control joints, which are saw cuts made into the surface of the slab to control where the concrete will crack in a controlled manner.

To determine the appropriate depth for these control joints, a common thumb rule is to cut them at a depth of one-quarter to one-third of the thickness of the slab. For example, if the slab is 150mm thick, the depth of the joint should be between 40mm to 50mm.

It is important to ensure that the depth of the joint is not too deep, as this can result in inadequate aggregate interlocking, which is necessary to transfer loads effectively. On the other hand, if the saw cut is too shallow, there is a risk of random cracking occurring in the slab, which can compromise its structural integrity.

Therefore, it is crucial to follow the recommended guidelines when determining the depth of control joints to ensure that the concrete slab is able to perform as intended and withstand the loads it will be subjected to over time.

4. How to Cut the Control Joints

Before making joints in a concrete slab, it is important to calculate and mark the locations where the joints will be made. This is typically done using a chalk-line. To ensure consistency, it is important to ensure that all the segments created are of the same size and that the cuts are made in a straight line.

Using machines to make the joints is recommended, rather than relying on manual methods. When using water-cutting equipment, it is important to ensure that the water is running all the way down to the blade. This will help to ensure that the blade operates effectively and that the cuts are made cleanly.

When using a machine to create the joints, it is important to set the blade depth to the depth of the control joint. The concrete slab must be sawed following the chalk mark that was made earlier. This will help to ensure that the joints are straight and that they are located in the correct positions.

After the joints have been made, it is important to clean the saw cuts thoroughly. This will help to ensure that the joints are free from any debris or other materials that could interfere with their effectiveness. Additionally, filler material must be used to fill in the cuts. This will help to protect the reinforcement from corrosion and will also help to create a watertight joint.

How to Cut Control Joints in Concrete Slab?
Fig 2: Sealing of control joints.

Tips for Making Control Joints

When working with saw blades, it’s important to take proper precautions to ensure their longevity and safety. One key tip is to avoid twisting the saw blade, as this can cause damage and reduce its effectiveness. Additionally, it’s important to keep the blade from spinning in the cut, as this can increase wear on the bond.

When cutting concrete that contains heavy rebar, it’s important to use blades with soft metal segment bonds. These types of blades are better suited to handle the challenges posed by rebar, and will help ensure a clean and effective cut.

Finally, when working with saw blades, it’s crucial to always use the required personal protective equipment (PPE). This can include things like safety glasses, ear plugs, gloves, and other gear that will help protect you from potential hazards. By following these guidelines, you can help ensure your safety and the longevity of your saw blades.