The task of rate analysis for cement mortar involves estimating the required amount of materials, namely cement and sand, for a given proportion of the mortar. Various proportions are used, such as CM 1:2, 1:4, 1:6, 1:8, among others. In order to determine the quantity of cement and sand needed for 1m3 of the cement mortar, it is necessary to calculate the amount required for 1.3m3 due to the presence of voids in the sand in its dry state. This means that for 1m3 of wet cement mortar, 1.3m3 of cement and sand is needed. The calculation of the cement and sand quantity is thus based on this amount for 1.3m3 of cement mortar.

Estimation of Materials for Cement Mortar:

To calculate the quantity of cement and sand needed for a cement mortar, there are specific steps that need to be followed. These steps ensure that the right amount of materials are used to achieve the desired strength and consistency of the mortar.

The first step is to determine the proportion of cement and sand to be used in the mortar. This proportion is usually given in the construction plan or can be determined based on the requirements of the project. The proportion of cement and sand is usually given as a ratio, for example, 1:4 or 1:6.

Once the proportion is known, the next step is to calculate the volume of mortar needed. This can be done by multiplying the area to be covered by the thickness of the mortar. The result is the volume of mortar required in cubic meters or cubic feet.

After calculating the volume of mortar required, the next step is to calculate the quantity of cement and sand needed. This is done by multiplying the volume of mortar by the proportion of cement and sand. For example, if the proportion is 1:6, the quantity of cement needed will be 1/7 times the volume of mortar, and the quantity of sand needed will be 6/7 times the volume of mortar.

Finally, it is important to add a margin for wastage and spillage. This margin can vary depending on the skill level of the workers and the complexity of the project. A common margin is around 10%. The final quantity of cement and sand needed will be the calculated quantity plus the margin for wastage and spillage.

By following these steps, it is possible to accurately calculate the quantity of cement and sand needed for a cement mortar, ensuring that the right amount of materials are used and wastage is minimized.

Cement Mortar

To calculate the quantity of cement and sand for CM 1:X, we need to follow a specific proportion where 1 represents the proportion of cement and X represents the proportion of sand. In this context, we can calculate the quantity of cement required for a particular project by using a specific formula.

The formula for calculating the quantity of cement required is as follows: Quantity of cement = (Cement ratio / Total ratio) x Volume of concrete, where the cement ratio is 1, and the total ratio is the sum of the cement ratio and sand ratio (1+X). The volume of concrete is calculated based on the dimensions of the structure that needs to be built.

By using this formula, we can determine the amount of cement that is required to make a specific volume of concrete for a given project. This calculation is crucial because it helps us to estimate the cost of the project and ensure that we have enough materials to complete the construction work.

Therefore, it is important to follow the correct proportion of cement and sand in order to achieve the desired strength and durability of the structure. By using the correct quantity of cement and sand, we can ensure that the concrete is strong, durable, and can withstand various environmental factors over time.

Rate Analysis for Cement Mortar -Calculate Quantity and Cost

The formula provided is used to calculate the quantity of cement needed for a particular construction project. The resulting quantity is given in terms of volume. However, in order to determine the number of bags of cement required, the volume needs to be divided by the volume of one bag of cement. This volume is measured at 0.0347 cubic meters per bag. By dividing the total required volume by this value, we can determine the number of bags of cement needed for the project.

Rate Analysis for Cement Mortar -Calculate Quantity and Cost

 Quantity of sand = 

Rate Analysis for Cement Mortar -Calculate Quantity and Cost


The given context provides a formula to calculate the quantity of cement in bags for a given proportion of CM 1:4. However, it does not provide any further information on the context or the specific use case for this calculation.

The formula suggests that the quantity of cement in bags can be determined by multiplying the total quantity of materials by the proportion of cement in the mixture. In this case, the proportion of cement is 1 part out of a total of 5 parts (1 part cement and 4 parts sand). Therefore, to calculate the quantity of cement in bags, one needs to divide the total quantity of materials by 5 and then multiply it by 1.

It is important to note that the given formula assumes a specific mixture ratio and may not be applicable in all situations. The context does not provide any information on the type of construction or the specific use case for this proportion of CM 1:4. Hence, it is important to seek expert advice and consider the specific requirements of each project before using any such formula.

Rate Analysis for Cement Mortar -Calculate Quantity and Cost

=7.492 bags Quantity of sand = 

Rate Analysis for Cement Mortar -Calculate Quantity and Cost

= 1.04 m3 of sand.

Estimation of Labour and Tools for cement mortar:

To create one cubic meter of cement mortar, a certain amount of skilled and unskilled labor is required. Specifically, 0.27 days of labor from a semi-skilled worker is necessary for the mixing process, while 0.26 days of labor from an unskilled worker is required for carrying the cement, sand, and water. In addition to manual labor, a mechanical mixer may also be used to assist with the mixing process. The hire charges for this mechanical mixer can be lumped into a single payment, which is typically equivalent to 0.27 days of labor for mixing one cubic meter of mortar.

Rate Analysis of cement mortar:


The analysis of the cost of cement mortar involves calculating the rate of cement and sand, which are then multiplied by their respective quantities. Additionally, the cost of labor and tools and tackles required for the cement mortar is also taken into consideration. It is important to note that the cost of cement, sand, labor, and tools is dependent on the local availability and rates.

Once the quantities of cement, sand, labor, and tools are determined, they are multiplied by their respective rates. To account for the contractor’s profit margin, a markup of 10-20% is added to the total cost. The resulting sum of these costs is taken as the total cost of 1 cubic meter of cement mortar. This information is typically presented in a document or file for reference.