Step by Step Guide of the Cable Tray work plan

Explain in detail the steps that must be taken to ensure that the task is carried out safely (include drawing and sketches where
required, include pre commencement of work activities and the work itself in a chronological manner).

A. Verify IFC drawings availability
B. Verify Documents for QC material receiving inspection
C. Mobilization of equipment
D. Transport of materials loading & Unloading
E. Cable tray Installation

Step by Step Guide of the Cable Tray work plan for Plants and Refinery Projects

  1. Secure work permit ( proper color coding for electrical equipment and third party certificate are accepted),
  2. Transport materials from Contractor warehouse to site ( Follow proper traffic signs & signals, turn on hazards light. only
    competent and certified rigger and operator should do the lifting, ensure one flag man for traffic control during activity. Provide
    barricade with signage)
  3. Layout Cable tray routing as per IFC drawings
  4. Fabrication of Cable tray supports per design/ detail drawings (Ensure permit to Hot work must be obtain prior to start the
    activity conduct toolbox talk prior to the task to be done. And wearing of PPE to all personnel. All Extension Cables tools and
    equipment’s must be inspected and in good condition)
  5. Installation of Cable tray supports (Drilling for support installation. Welding activity when required, ensure welding cables and
    extension is free from any defects, area must be barricaded and ensure presence of fire extinguisher and fire blankets on working
    area and assign one fire watch man for the activity. Removed all combustible materials on working area. To avoid fire hazards use
    proper PPE Welding mask and face shield as required in hot work activity)
  6. Installation of cable tray and accessories (Use of Full Body Harness 100% tie off when working at height, all tools must be
    inspected and good condition. Ensure when using of portable ladder maintain proper slope 4: I and one person holding 011 it when in
    ascending /descending use proper PPE. Grounding Bonding Installation (use proper PPE, use Full Body Harness 100% tie off when
    working on elevated area. When using portable ladder observed proper slope and make sure one person holding on the ladder. Use
    appropriate tools for the job)
  7. Cable Tray covering (after cable pulling) (Use of Full Body Harness 100% tie off when working at height, all tools must be
    inspected and good condition. Ensure when using of portable ladder maintain proper slope 4:I and one person holding on it when in
    ascending /descending use proper PPE)
  8. Daily housekeeping (Full supervision on the area remind personnel for safe working and good housekeeping on the area should
    be done before and after the work )
  9. Request for QC inspection (RFI